Coulee Creek
Problem This Lethbridge land developer was constructing a series of residential
condominiums in 2 phases and needed deck and entry foundations installed as
well as light stands. Portions of
the development were already paved, backfill was completed and winter weather
was approaching.
Solution We were able to engineer, design and install a screw pile solution for every
element required. We completed the
installations quickly with no disruption to other areas of the development
process. Because there was no
curing process to circumvent, load was able to be applied to the deck and entry
foundations immediately, making it simple for the developer to easily meet time
lines.
|
 |
|
 |